Step 9:  Finalize Details

Modular homes built to the UBC code are the most complete when they leave the factory.  Usually, all electrical, plumbing, energy, drywall, floor, wall, ceiling, roofing and siding systems are completed in the factory.  Completing as many tasks in the factory as possible using routine procedures ensures a higher level of quality control and the lowest possible construction costs per square foot.  This means a more affordable home price and fewer

.
subcontractors at the construction site.  Given even the highest degree of factory completion, certain tasks must be completed at the building site in order to integrate the home with the lot and the surrounding neighborhood

          Consider the Following:

1. Adjust windows and doors as required.
2. Complete all mechanical installations and connections which including:
heating, plumbing, electric, phone, venting, exterior lights, cable. doorbell, thermostat, and smoke detectors. 
3. Check for leaks by air pressurizing the systems before water pressurizing plumbing and heating.
4. Repair any glass or mirror items that may have broken during transport
5. Repair any cosmetic cracks resulting from transport

6. Finish any touch up  painting, interior and exterior, that may be needed.
7. Install light bulbs in all fixtures inside and outside.
8. Install and connect all appliances including water heater and HVAV.
9. Build garage, driveway, steps and all outdoor cement work including porch. 
10. Finish Grade/ Landscaping. This is for the work necessary to finish thegrade for drainage and landscaping.
11. Install any fencing at this time.